How long does it take to build a website? Realistic timelines

How long does it take to build a website? Realistic timelines
Short answer

A landing page usually takes 1 to 2 weeks, a small business website 3 to 6 weeks and an online store 4 to 10 weeks. Design alone takes 1 to 3 weeks for 5 to 8 pages. The biggest factor is not the build itself but how quickly content, feedback and approvals arrive.

Clients always ask how long their website will take. The honest answer depends on the size of the site and on how fast decisions get made. Here are the timelines we see on real projects.

Typical website timelines

Type of siteTypical timeline
Website design only (Figma, 5 to 8 pages)1 to 3 weeks
Landing page1 to 2 weeks
Small business site (5 to 8 pages)3 to 6 weeks
Site with blog or CMS4 to 8 weeks
Online store4 to 10 weeks
Large custom site or redesign2 to 4 months

These are typical ranges for a custom design and build, not template setups. A site you put together yourself on a template or an AI builder can go live in days, but most of that time still goes into writing content.

How long does it take to design a website?

Design alone, without development, usually takes 1 to 3 weeks for a site of 5 to 8 pages. The homepage takes the longest, because it sets the visual direction; inner pages reuse its components and go faster. Mobile layouts come after the desktop pages are approved.

The number of revision rounds decides most of that range. One person giving combined feedback within a day or two keeps the design phase at the short end. A homepage designed in Figma starts at $385 on our web design service, plus $120 for each extra page.

A week-by-week example

WeekWhat happens
Week 1Brief, page list and sitemap, homepage design
Week 2Homepage revisions, inner page designs
Week 3Mobile designs, development starts
Week 4Development, CMS and forms, testing on all screen sizes
Week 5Content goes in, review on a staging link, launch

This is a realistic plan for a custom 6-page business site, assuming the copy is ready and feedback comes back within one or two days. Each week of waiting for content or approvals moves the launch by a week.

Real timelines from our projects

  • Webflow homepage: about 2 weeks from an approved Figma design to a live, responsive page. Our Webflow development starts at $840.
  • Shopify store: a sustainable home goods brand with 80 products went from start to launch in 12 days. Store timelines on our Shopify development service are quoted per store.

The phases of a website project

  1. Brief and planning: pages, goals, examples (a few days).
  2. Design: homepage first, then inner pages, with revisions (1 to 3 weeks).
  3. Development: responsive build, CMS and integrations (1 to 4 weeks).
  4. Content and review: copy, images and final feedback.
  5. Launch: domain, redirects, SEO setup and testing.

Brief and planning

This is where the scope is set: which pages the site needs, what each page should do, who the audience is and which sites you like. A clear page list here is the single biggest thing that keeps the rest of the timeline on track.

Design

We design the homepage first, because it sets the look for everything else. Once it is approved, the inner pages go much faster. Most of the design time is spent on revisions, so clear, combined feedback from one person shortens this phase a lot.

Development

The approved design is built as a real, responsive website on the chosen platform, with the CMS, forms and any integrations. Every page is checked on desktop, tablet and mobile. Larger sites, ecommerce and custom features take longer here than in design.

Content and review

Final copy and images go in, and you review the site on a staging link before it goes live. This phase is short when content is ready and long when it is still being written.

Launch

The domain is connected, old URLs are redirected if you are replacing a site, and basic SEO is set up: page titles, descriptions, a sitemap and analytics. A final round of testing covers forms, links and speed. Our guide to the website design process walks through each step in more detail.

Does the platform change the timeline?

Less than most people expect. Webflow, WordPress and Shopify can all be built in similar timeframes for a similar scope. What changes the time is the number of unique page layouts, the amount of CMS content, ecommerce setup and custom features. A redesign of an existing site adds work for content migration and redirects.

What slows a project down

  • Missing copy and images. This is the most common delay by far.
  • Slow feedback rounds or too many people giving feedback.
  • New pages or features added in the middle of the project.
  • Waiting for access to the domain, hosting or old website.
Projects where the client sends all copy and images before design starts are often finished in half the time.

What to prepare before the project starts

  • A page list and the main goal of each page.
  • Your logo files, ideally vector, and brand colors and fonts.
  • All copy, or a clear plan for who writes it and when.
  • Photos and videos, or a budget for stock images or a shoot.
  • Access to your domain, hosting and any old website.
  • Two or three websites you like, with a short note on why.

How to launch faster

  • Write a clear brief with a page list. Our design brief guide helps.
  • Prepare content early.
  • Pick one person to approve designs.
  • Launch the core pages first and add the rest later.

What happens after launch

A website is never really finished. Plan time after launch for small fixes, new content and checking how visitors use the site. If you are replacing an old site, keep an eye on search traffic in the weeks after launch, because that is when missing redirects show up. We explain how to protect rankings in website redesign and SEO.

Related guides

Planning a new website?

We design in Figma and build on Webflow, WordPress or Shopify with clear timelines.

Web Design →

FAQ

Usually 3 to 6 weeks for a custom design and build of 5 to 8 pages.

About 1 to 2 weeks, depending on content and revisions.

Design alone usually takes 1 to 3 weeks for a site of 5 to 8 pages, with the homepage designed first and the inner pages after it is approved.

A single landing page can be. A full custom site usually cannot without cutting design or testing.

Sources

Based on our client website projects.